Amidst strong competition in the industry, JGSI won the bid for the extensive production drilling project in Hinatuan Mining Corporation.
This project involves drilling 1055 holes into nickel laterite with a total aggregate depth of 16,860 m. To successfully complete this project within the time frame given, JGSI will mobilize 15 portable mechanical rigs.
With grateful hearts, JGSI promises to conduct this project with utmost excellence and dedication.
So help us God!
After two months of hard labor, JGSI has finally completed the GHD Davao Bulk Water System geotechnical drilling project. This project is composed of drilling 22 inland holes and 4 river holes.
This project proved to be a challenge due to the large spacing between the holes and the fluctuations of the river current. But JGSI's strong teamwork and dedication helped it finish the project right on schedule.
Great job JGSI team!